PROJECT
Nammoona Landfill Cell 6A
51,250 | 770
Size (m2) | lm
Richmond Valley Council
Client
Casino NSW
Location
GCL, HDPE, Geotextile, Geomcomposite & HDPE Pipe
Materials Installed
Synergy Resource Management
Head Contractor
1.5 Months
Duration
Tasked with supply & installing Geosynthetics to the Nammoona Landfill project in Casino NSW.
Enviro Lining encounted some difficulties with the weather conditions faced at the time of installation. Working with the contractor and our Project Management Team, Enviro Lining managed to minimise the impacts of the major weather events.
All in all a successful completion of yet another landfill for Synergy Resource Management, with no failures or issues with Geosynthetic Material supplied or Installation CQA testing.